The current proposal

Project Delta, in plain language.

What is publicly identified, what remains undisclosed, what the applicant proposes, and why residents are asking for closer review.

Project parties and filing facts

What the current record identifies.

Unknown or incomplete items are labeled rather than guessed. The conceptual filing may change during review.

Applicants / Property Owners:
DFC Stokes, LLC and DFC Stokes 2, LLC
Developer:
Engineered Land Solutions (ELS)
Project Manager / Public Project Lead:
Drew Nations, President and CEO of Engineered Land Solutions
End User of the Data Center:
Not publicly identified
Location:
Parcels near U.S. Highway 311, Tuttle Road, Coon Joyce Road, and the Dan River near Walnut Cove
Site Area:
Approximately 1,848.741 acres
Buildings:
Multiple data-center buildings and accessory structures; the current filing does not specify a final building count
Combined Gross Floor Area:
Not specified in the current July 2026 filing
Maximum Height:
80 feet for principal buildings; specified mechanical, communications, utility, and safety appurtenances may extend higher
Utility Infrastructure:
Proposed accessory uses include substations, electrical and natural-gas infrastructure, fiber, backup generation, batteries, equipment yards, fuel and water storage, and related systems
Intended Use:
A data-center campus for storing, retrieving, managing, and processing digital data, with associated infrastructure and accessory uses
Requested Zoning:
Residential-Agricultural (R-A) to Heavy Manufacturing Conditional Zoning (M-2-CZ)
Important distinction: The project website’s job, revenue, infrastructure, water, traffic, and environmental statements are applicant claims. The county filing and any final adopted conditions determine what is actually requested or legally enforceable.

Why residents are concerned

The questions extend beyond one zoning label.

Residents have raised concerns about the project’s cumulative, long-term effects and the amount of information still unavailable before a final decision.

Scale and rural compatibility

The proposed acreage and industrial intensity are unusually large for a rural area of farms, forests, homes, and small communities.

Electric demand and customer costs

Residents want independently reviewed load projections, upgrade responsibilities, rate protections, backup-generation details, and disclosure of who bears stranded-cost risk.

Noise and backup generation

Questions remain about cumulative low-frequency sound, generator testing, emergencies, complaint response, continuous monitoring, and enforceable remedies.

Water, waterways, and stormwater

Residents are asking how cooling, construction, impervious surface, erosion, runoff, floodplain limits, groundwater, and the Dan River will be protected over full buildout.

Air quality and public health

Backup power, construction activity, heat, emissions, and combined industrial burdens are among the health-related issues residents want analyzed before approval.

History and cultural resources

The surrounding landscape is tied to Saura history, Black farming communities, the Hairston and Bailey families, cemeteries, archaeology, and the county’s rural identity.

Economic assumptions

Residents want transparent calculations for tax revenue, jobs, incentives, depreciation, public-service costs, utility investments, and the timeline for reaching full buildout.

Unknown operator and final design

The end user, final building program, combined floor area, full power demand, construction phasing, and some operating details have not been publicly identified.

Enforcement and accountability

Proposed conditions matter only if they are measurable, independently verified, publicly reported, enforceable, and paired with effective remedies for noncompliance.

What residents can do now

Take a clear next step.

Choose one action—or several—to help neighbors follow the record and participate in the public process.

01

Sign the main petition

Add your name to Protect Stokes County! Reject Project Delta!

Take this step ↗
02

Review the existing petition

See the No Data Center in Walnut Cove petition and its community support.

Take this step ↗
03

Contact commissioners

Call or email each member of the Stokes County Board of Commissioners.

Take this step →
04

Attend a public meeting

Check upcoming Board of Commissioners dates, agendas, and packets.

Take this step →
05

Share with neighbors

Use the share button to send this page to people across Stokes County.

06

Get involved

Send a message to the leaders of Stokes County Strong, Data Center Wrong.

Take this step →
Stay civil and peaceful.

Passionate advocacy never justifies hateful rhetoric, harassment, threats, or political violence.

Read both the filing and the claims

Go directly to the source documents.

Official county filing

Application, proposed conditions, buffer exhibit, conceptual site plan, meeting report, and parcel materials.

Open county materials ↗

Developer position

Project Delta’s website presents the developer’s benefits, commitments, FAQs, and economic projections.

Open developer website ↗